Challenge
Severe surface bumps emerged at high-speed sections of an F1 track due to subsurface settlement. Mandatory remediation was required, but strict racing regulations and timelines made conventional resurfacing impossible.
Solution
Geobear utilized precision geopolymer injections to lift the track with millimeter-level control. Guided by live laser monitoring, the zero-excavation treatment permanently eliminated surface dips while preserving the high-performance asphalt.
of precise vertical lift achieved to eliminate critical high-speed dips.
treatment area completed in just three weeks, avoiding a massive 4,500 m² milling operation.
dynamic testing verified a significant reduction in peak vertical accelerations and a restored smooth ride quality.
This project involved the precision re-leveling of an international Formula 1 racing circuit in the Middle East, one of the most demanding operational environments for pavement performance and geometric tolerances.
The track, originally constructed in 2004, was designed to deliver exceptional grip through the use of high PSV aggregates and a robust pavement structure over predominantly limestone subgrade conditions
More than two decades after construction, the track remained structurally sound and retained its original surfacing. However, localized geometric defects began to emerge—specifically surface undulations (“bumps”) at critical high-speed sections.
Main Contractor: CEBARCO
Solution Provider: Geobear
Installation Period: ~2 weeks
Treatment Area: ~840 m²

During a major racing event, drivers reported significant “bumps” at critical track sections,
These defects were not superficial—they were driven by long-term structural and geotechnical mechanisms, including:
The result:

Mr Duncan MacKillop, Engineering Manager for Cebarco
The standard approach—mill and relay asphalt—was immediately ruled out.
Reasons were practical, not theoretical:
Traditional methods were too slow, too expensive, and too disruptive.
With conventional resurfacing ruled out, the project required a solution that could directly address the root cause—subsurface deformation—while preserving the existing high-performance asphalt surface. The selected approach was a precision Geopolymer injection re-leveling system, designed to locally lift and stabilize the track with millimeter-level control.
The starting point was accuracy. Without that, the rest fails.
From this:
Instead of treating large areas blindly, the solution focused only where needed.

This is where most projects fail. Control.
The objective:
Real-time monitoring and feedback loop
This was a live system—not install-and-hope.
Laser monitoring (±2.5 mm accuracy) at each active injection point

After each injection:
This created a closed-loop control system:
Inject → Monitor → Verify → Adjust → Continue
Verification on this project was not treated as a formality—it was the critical proof that the intervention actually worked under real operating conditions. Given the sensitivity of a Formula 1 track, success could not be claimed based on visual inspection or survey data alone. It required multi-layered validation, combining geometric, dynamic, and real-world performance evidence.
The most meaningful verification was how the track behaved under speed—not how it looked.

Pre-treatment:
Indicative of sharp dips and uneven geometry

While dynamic performance proves functionality, geometry proves compliance.
Outputs included:

“Due to the specialist material and construction specifications for the F1 track installation a conventional track relaying operation was logistically infeasible in the available timescales.
To resolve the problem Cebarco contacted Geobear who provided cost effective proposals to use resin injection techniques to re-level the track. Works were carried out, at short notice, to 840 square metres of track during a three week period in January 2024 and the track alignments were successfully rectified using a close tolerance laser controlled methodology, lifting the track by amounts ranging from 1 millimetre to 16 millimetres.
The processes undertaken by Geobear are technically ingenious and innovative and are carried out with meticulous planning and expertise by highly experienced teams using specialist equipment. Cebarco would have no hesitation in recommending Geobear for similar projects.”
- Mr Duncan MacKillop, Engineering Manager for Cebarco, who was leading this project from Cebarco.
This project demonstrates that even in the most demanding engineering environments, complex surface defects can be resolved without reconstruction.
Faced with mandatory remediation of localized surface undulations ("bumps") at critical high-speed sections of an international Formula 1 track—driven by deep-seated geotechnical issues like settlement and concrete creep—the project was under strict time pressure with zero tolerance for failure ahead of the next racing cycle.
Geobear's precision releveling solution provided an innovative and cost-effective alternative that addressed the surface deformation while preserving the high-performance asphalt. Performance was confirmed through multi-layered validation. Geometric verification confirmed the elimination of previously recorded dips (up to 16 mm). More critically, dynamic performance testing using an accelerometer-equipped vehicle at ~105 km/h demonstrated a significant reduction in peak vertical accelerations, confirming the elimination of abrupt dynamic inputs and achieving a smoother, more uniform response profile.
Completed during a three-week period in January 2024, the project successfully rectified the track alignments. The client, CEBARCO, concluded that Geobear’s processes are "technically ingenious and innovative" and set a new precedent for non-disruptive, high-precision remediation in the most demanding operational environments.
Get in touch to discuss the details with us. Our professional engineering team are ready to listen and discuss options.