Ground improvement beneath interlocking pavement in Abu Dhabi

Challenge

Weak ground beneath interlocking pavement created a settlement risk at an operational educational facility with buried services crossing the treatment areas.

Solution

The Geobear Ground Improvement solution used staged injection to improve ground support beneath existing paving while the facility stayed operational.

+42.7%

Combined mean N60

+149.8%

Weak-zone mean N60

~7.0 m

MASW verification depth

Background

An educational facility in Abu Dhabi needed to address settlement risk beneath the interlocking pavement beside its buildings. The facility remained in use during the works, so managing access and protecting buried services shaped how Geobear planned and delivered the treatment.

The project targeted weak and variable ground beneath three pavement areas. The engineering objective was to improve support beneath the paving and verify the ground response with tests before and after treatment. Geobear recorded completion in July 2026.

Challenge

Two pre-treatment dynamic cone penetration testing (DCPT) profiles showed that ground resistance varied with depth and between the test locations. The lowest-resistance interval identified in the assessment was approximately 3.0 to 4.5 m below ground level. The combined mean N60, the processed indicator used to compare penetration resistance, was 6.28 in this interval before treatment.

Electrical, drainage, plumbing and mechanical services ran beneath the paving. Manholes and drainage grates also constrained where the team could drill. Geobear had to place drilling points around those features, control access to the working areas and monitor the pavement for movement.

Interpreted ground model

Chart showing an interpreted ground model based on DCPT and independent surface-wave surveys

Figure 1. Interpreted ground model based on DCPT and independent surface-wave surveys.

The model shows the weak interval identified in the paired tests and the depths covered by the verification evidence. The ground may vary between test locations. Soil types and layer boundaries remain undetermined.

The Geobear ground improvement solution

Geobear designed a solution to improve ground support beneath the existing pavement while keeping the facility operational. The team used staged injection through local drilling points in three pavement areas. The completion record lists 61 injection locations. During treatment, the team observed ground behaviour and monitored the pavement for surface lift.

Working around buried services

Before drilling, Geobear used ground-penetrating radar (GPR) and a cable avoidance tool (CAT) to locate buried services. The team adjusted the drilling positions around the detected services, manholes and drainage features. Site controls included marked work areas, controlled access, equipment checks and service-location checks.

Why staged injection suited this site

An excavation-and-replacement approach would have required opening the paving, working around buried services and reinstating the affected surface. Staged injection let Geobear reach the weak ground through local drilling points. This limited the working footprint at a facility that needed to remain in use and had limited space around its services.

A Geobear tech installing an injection tube at a treatment point.

Installing an injection tube at a treatment point.

A Geobear tech performing injection works within a marked work area.

Injection works within a marked work area.

Results

Penetration resistance increased

Geobear compared paired DCPT profiles at two locations. The processed dataset reports N60 at 0.1 m depth intervals. Combined mean N60 rose from 11.44 to 16.32 across the assessed depths, an increase of 42.7%. Both test locations recorded higher mean N60 values after treatment.

Chart showing DCPT testing before and after figures
Figure 2. Mean N60 before and after treatment across the assessed depth intervals.

DCPT assessment

Mean N60 before Mean N60 after Increase
Combined assessed depths 11.44 16.32 +42.7%
Initially weak interval (3.0–4.5 m) 6.28 15.69 +149.8%
Test 1 (1.6–7.5 m) 12.69 16.68 +31.4%
Test 2 (1.0–7.5 m) 10.30 16.01 +55.4%

 

The strongest response was in the initially weak 3.0 to 4.5 m interval, where combined mean N60 increased from 6.28 to 15.69. Across both profiles, N60 improved at 88.9% of the assessed depth points. The paired tests show how penetration resistance changed at those locations.

Independent surface-wave verification

An independent geophysical survey compared multichannel analysis of surface waves (MASW) sections before and after treatment along three lines. MASW estimates shear-wave velocity, which helps interpret variations in ground stiffness along a survey line. Each pair uses a common velocity scale for comparison.

The independent assessment confirmed improvement to approximately 7.0 m below ground level. The MASW sections show conditions along the survey lines and complement the penetration-resistance measurements at the two DCPT locations.

Chart showing MASW survey line 1 before and after treatment.

Figure 3. MASW survey line 1 before and after treatment.

Figure showing MASW survey line 2 before and after treatment.

Figure 4. MASW survey line 2 before and after treatment.

Chart showing MASW survey line 3 before and after treatment.

Figure 5. MASW survey line 3 before and after treatment.

Do you have uneven interlocking pavers?

Don't let unstable ground put your business at risk. Our commercial team can provide a clear assessment and a fast, effective solution tailored to your operational needs.

Bear pointing Bear pointing