Ground improvement of settled foundations, Jebel Ali, Dubai

Challenge

A leaking water tank washed out the soil beneath a Jebel Ali facility, causing 16 cm of differential settlement and structural cracking. Traditional excavation was too costly and highly disruptive.

Solution

Geobear injected an expanding geopolymer resin directly into the weakened soil. This zero-excavation solution rapidly compacted the loose sand, restored bearing capacity, and permanently stabilized the foundations without displacing occupants.

3.8x

Increase in bearing capacity

16 cm

Of halted differential settlement

0

Excavation required

Background

We collaborated closely with KSI Structures Engineering Solutions, a respected UAE consultant. KSI introduced us to the project and played a key role in both design support and technical verification. Their expertise ensured the solution was robust and aligned with structural expectations, enhancing the project’s success.

A labour accommodation facility in Jebel Ali, Dubai experienced severe differential settlement affecting multiple pad foundations, leading to visible structural damage and serviceability concerns.

The issue was traced to subsurface weakening caused by water leakage from a nearby tank, which altered soil conditions beneath the structure.

Geobear was appointed to stabilize the foundations using its geopolymer injection solution, providing a fast, non-disruptive alternative to conventional underpinning.

Interior view of building construction in Jebel Ali, UAE

Interior view of building construction in Jebel Ali, UAE

Challenge

Severe differential settlement

  • Up to 16 cm differential settlement between adjacent footings
  • Total settlement locally reaching ~30 cm
  • Concentrated settlement observed along one foundation row (as highlighted in layout drawings)

Root cause

Water leakage led to:

  • Soil softening and washout
  • Formation of weak zones and possible cavities
  • Reduction in bearing capacity beneath foundations

Observed damage

  • Cracking and displacement at structural elements
  • Distortion at column bases and foundation interfaces
  • Signs of ground instability around footings 

UAE cracks in building cement caused by differential settlement

Damage to building cement ceiling caused by differential settlement

UAE damage to building caused by differential settlement

UAE damage to building column caused by differential settlement

Ground investigation findings

Geotechnical testing (DCPT)

Very low resistance at foundation depth:
Equivalent SPT N60 ≈ 2 – 11 (loose soil condition)

UAE Jebel Ali geotechnical testing DCPT findings
Geophysical survey (MASW)

Identified a weak layer between 1.5 m and 2.5 m depth

Shear wave velocity:
129–300 m/s (low stiffness zone)

Interpretation

The structure was founded on loose to medium sand weakened by water ingress.

Competent strata existed below ~4 m depth, confirming a localized problem.

Overall, the MASW results independently verify that the treatment eliminated the weak zone and restored ground stiffness beneath the foundations.

Solution

The Solution: Geobear ground improvement

Geobear implemented a targeted ground improvement program using expanding geopolymer material.

Execution approach

  • Injection depth focused around 1.5 m below foundation level
  • Multiple injection points across affected foundations


UAE Jebel Ali injection cross section diagram plan

UAE Jebel Ali injection points in interior building floor

Method advantages

  • No excavation or structural dismantling
  • Minimal disruption to occupants
  • Immediate soil strengthening upon injection

Mechanism

The geopolymer:

  • Expands and compacts surrounding soil
  • Fills voids and weak zones

Increases:

  • Density
  • Stiffness
  • Shear strength

Results

Verification and testing

Pre and Post injections DCPT testing and MASW survey were carried out to verify the effectiveness of the treatment

1. DCPT / SPT improvement

Test 1 results

  • N60 increased from ~4.8 → ~18.4
  • Allowable bearing capacity:
  • 82 kPa → 309 kPa (~3.8× increase)

UAE Jebel Ali DCP N60 values before and after resin injection chart

Results

Condition Average N60 ϕ (deg) q_ult (kPa) q_allow (kPa)
Before Injection ≈4.77 ≈21.3 ≈246 ≈82
After Injection ≈18.38 ≈30.9 ≈927 ≈309

 

2. MASW (Geophysical verification)

A MASW survey was carried out to assess ground stiffness before and after treatment. Results identified a low-velocity zone at 1.5–2.5 m depth (Vs ≈ 129–300 m/s), corresponding to weak, moisture-affected soils responsible for the observed settlement.

Following Geobear’s Geopolymer Injection, a clear increase in shear wave velocity was recorded within the same depth range, confirming improved soil stiffness, density, and continuity.

Deeper layers (>4 m) remained consistently dense and unaffected, confirming that the issue was localized and successfully targeted.

Overall, the MASW results independently verify that the treatment eliminated the weak zone and restored ground stiffness beneath the foundations.

UAE Jebel Ali MASW testing results diagram

Engineering interpretation

The treatment achieved:

  • Significant increase in effective stress conditions
  • Improved friction angle: ~21–23° → ~31–32°
  • Transition from loose to medium-dense soil behavior

This directly translated into:

  • Higher bearing capacity
  • Reduced compressibility
  • Improved foundation performance

Improvement analysis from MASW scanning

Treatment zone: 1.5 m - 3.5 m depth | Method: S-wave velocity (Vs) comparison, MASW
 
Summary metrics — treatment zone (1.5-3.5 m)

Pre-grout avg Vs Post-grout avg Vs Avg Vs gain Shear modulus gain
~133 m/s ~233 m/s +100 m/s ~3.1x

 

Versus comparison by sub-interval

Pre- and post-grout shear wave velocity at 0.5 m sub-intervals across the treatment window. Post-grout values consistently exceed 200 m/s throughout, confirming effective ground improvement.

Graph of UAE Jebel Ali Pre- and post-grout Vs by depth sub-interval

Improvement metrics

Vs improvement ranges from +69% to +80% across the zone. Since shear modulus G is proportional to Vs², the corresponding stiffness gain (G multiplier) ranges from 2.9x to 3.2x, indicating substantial densification.

UAE percent Vs improvement and shear modulus multiplier per sub-interval

Detailed results

Sub-interval Pre-grout Vs Post-grout Vs Vs gain (%) G multiplier
1.5 - 2.0 m ~130 m/s ~220 m/s +69% x2.9
2.0 - 2.5 m ~135 m/s ~240 m/s +78% x3.2
2.5 - 3.0 m ~140 m/s ~245 m/s +75% x3.1
3.0 - 3.5 m ~125 m/s ~225 m/s +80% x3.2
Zone average ~133 m/s ~233 m/s +75% x3.1

 

The core of the treatment zone (1.5.0-3.5 m) exhibits the strongest response (69-80% Vs), consistent with grouting and lateral confinement being most effective at depth.

Post-grout Vs values of 220-245 m/s place the treated material firmly in the medium-dense to dense sand range. The shear modulus improvement of approximately 3.1x across the treatment zone is consistent with successful permeation or compaction grouting.

Results

Structural performance

  • Foundations stabilized without excavation
  • Settlement progression arrested
  • Improved load distribution across footing system

Ground performance

  • Weak zone successfully treated
  • Soil stiffness and density significantly enhanced
  • Verified by both geotechnical and geophysical methods

Project success

  • Delivered with minimal disruption
  • Avoided costly underpinning or reconstruction
  • Achieved >3× improvement in bearing capacity

Discuss your project with an expert

Don't let unstable ground put your business at risk. Our commercial team can provide a clear assessment and a fast, effective solution tailored to your operational needs.

Bear pointing Bear pointing