5,576m² retail park car park stabilised with minimal disruption

Challenge

A busy retail park, built on a 3-6m deep landfill, had severe settlement across its 5,576m² car park and service areas, creating H&S risks. Traditional excavation was "inconceivable."

Solution

Geobear injected geopolymer resin at depths of 1m-2m to compact the unstable landfill material. A separate operation lifted a settled dock leveller by 150mm back to level.

5,576m²

Total area stabilised

150mm

Lift on the dock leveller

7 weeks

Project completion time

Only 6-12

Parking bays restricted at a time

Background

Woodfields Retail Park in Bury, a busy site with major stores like Tesco, was suffering from severe undulations. The access road, car park, and service areas, constructed in the 1990s on a former landfill tip, were all affected.

Settlement caused widespread "ponding" and created significant health and safety concerns, especially in the service yard.

Challenge

Ground investigations confirmed the site was built on 3m-6m of "historical, random deep landfill." This non-homogenous and poorly compacted sub-base was causing non-linear settlement under load. The service yard dock levellers were unusable, and defective drainage lines were contributing to the problem.

The traditional solution—excavating the existing construction, replacing the deep fill, and re-surfacing—was "inconceivable" as it would shut down the busy retail park.

At any given time, only 6-12 parking bays were restricted, allowing the retail park to remain fully operational and shoppers to be "barely impacted."

Solution

Geobear delivered a 5,576m² ground improvement solution with minimal disruption. For the car park and entrance roundabout, geopolymer resin was injected in a 1m horizontal grid pattern. The injection depth was predominantly 1m (to treat to 1.5m) but extended to 2m in weaker areas over the deep landfill to ensure compaction.

For the service yard, a different geopolymer material was used to lift a settled dock leveller. Injecting at 1m centres and monitoring with lasers, the unit was precisely raised by 150mm back to its datum level.

Results

The entire large-scale project was completed in just seven weeks. The key benefit was the minimal disruption; treated areas were handed back immediately.

At any given time, only 6-12 parking bays were restricted, allowing the retail park to remain fully operational and shoppers to be "barely impacted." The success of the ground improvement was verified by the client using CBR testing.