Ports & Harbours
Challenge
Soft, waterlogged soils beneath a superyacht shipyard caused slab cracking and settlement, threatening 250-tonne cradle operations — traditional piling would have required costly shutdowns and months of disruption.
Solution
Geobear injected expansive geopolymers to 4.5 m depth, increasing bearing capacity by 28%, eliminating voids, and delivering full dockyard stabilisation without interrupting yacht production.
        Increase in allowable bearing capacity (DCP verified)
Targeted injections to 4.5 m depth
Yacht production continued throughout phased delivery
A leading superyacht manufacturer faced structural challenges at their dockyard. The increasing size and weight of vessels had placed extraordinary loads on the yard’s hardstandings. Over time, concrete slabs began to crack, sink, and deform due to soft underlying soils and water ingress.
This created significant operational risk. Yachts in cradles needed to traverse the site, but uneven slabs introduced dangerous stresses to the cradles and the vessels themselves.
Two shipyards were assessed:
The project demanded a solution that could achieve deep ground improvement under live operational conditions. Yacht production schedules could not be interrupted, so works had to be carried out in phases that allowed continuous use of the dockyard.
The load requirements were extreme: up to 250 tonnes transferred through yacht cradles and cranes. Boreholes confirmed that the underlying soils were inadequate, presenting a high risk of further slab failure if left untreated.
Two slab types, each with different defects, required tailored design approaches. Dockyard A’s thicker slabs had extensive cracking at slab edges and corners, while Dockyard B’s block paving system had deformed under crane loads. Both scenarios pointed to the need for deep, multi-level ground strengthening.
Environmental factors also shaped the solution. Situated in a marine environment, the repair method needed to be completely inert, fast-curing, and environmentally approved to prevent any risk of leachate or contamination. Traditional piling was ruled out because:
Geobear designed and implemented a multi-phase ground improvement programme tailored to the site’s specific challenges.
The process began with a trial area, where geopolymer injections were tested and validated by pre- and post-treatment DCP testing. Once verified, the full scheme was delivered in multiple phases across both dockyards, ensuring operational continuity.

The project achieved significant technical, operational, and environmental outcomes:
Get in touch with our expert team today and discover how Geobear can extend the life of your critical infrastructure assets.
          
          
        info@geobear.com
0800 084 3503  
Company reg 10741472