Highways

Emergency ground strengthening at the M11 Girton interchange

Challenge

Severe voiding beneath the M11 northbound slip road threatened collapse at the Girton Interchange — traditional excavation repairs would have caused major disruption, delays, and safety risks.

Solution

Geobear stabilised the embankment with fast-curing geopolymer injection, restoring ground strength within tight tolerances, cutting disruption by five weeks, and reducing carbon emissions by 45%.

45% lower

Carbon saving - 45% lower CO₂ emissions vs. cementitious grouting

≥4 MPa

High strength: ≥4 MPa compressive strength achieved with ±5 mm surface tolerance

5 weeks faster

Rapid delivery 3-week programme — 5 weeks faster than excavation

Background

The northbound slip road at Junction 14 of the M11 — part of the Girton Interchange with the A14 and A428 — carries around 40,000 vehicles per day. As a critical link to Stansted Airport and strategic ferry ports, the route is a vital part of the UK’s Strategic Road Network.

Routine inspections by Highways England highlighted embankment issues at the M11 overbridge. Further ground investigation confirmed significant voiding beneath the carriageway close to the abutments. Left untreated, the defects risked severe settlement or even collapse, threatening safety and serviceability of the route at the same time as the adjacent A14 Cambridge–Huntingdon improvement scheme.

An urgent, non-intrusive solution was required to restore stability, avoid long closures, and maintain resilience on one of the busiest corridors in the East of England.

Challenge

  • Traffic impact: Closure of this section would have caused severe congestion on the M11, A14, and A428, affecting commuters and freight movements to Stansted and strategic ports.
  • Technical demands: Works required a compressive strength of 4 MPa while maintaining surface movement within ±5 mm to protect adjacent bridge wingwalls.
  • Investigative limits: Restricted traffic management precluded extensive ground investigation, requiring real-time adaptability during delivery.
  • Programme pressure: Emergency intervention was needed quickly, with minimal impact on the ongoing A14 improvement scheme.

Client insight

Geobear’s solution to the essential embankment repair at M11 Girton interchange has been a highlight of this year’s programme.

Karl Brooks - Highways England

Solution

Geobear, working with Highways England, WSP, Interserve, and Kier Highways, designed and delivered an emergency geopolymer injection scheme:

  • Injection process: Resin was injected beneath the carriageway to depths of up to 2.5 m, rapidly filling voids and reinstating soil contact.
  • Controlled expansion: “Trigger time” methodology ensured resin expansion remained predictable and pavement heave stayed within ±5 mm.
  • Real-time adjustments: Engineers adapted injection spacings and volumes to respond to unforeseen voiding conditions.
  • QA and monitoring: CCTV verified void fill, laser levels monitored surface movement, and Falling Weight Deflectometer tests confirmed post-treatment performance.
  • Accelerated delivery: Four crews worked in parallel across north and south abutments, enabling early completion.
m11-team-on-site

The works were completed two days ahead of programme, within budget, and with no safety incidents. The carriageway was stabilised, risk of collapse eliminated, and the motorway reopened every morning, ensuring disruption was limited to overnight closures only.

Compared with excavation, the project avoided at least five weeks of disruption. This aligns with the Volterra Transport Study, which found that faster road maintenance on high-demand routes like the M11 can deliver £640–£7,400 of user savings per kilometre of works, with national annual savings of £70m–£87m if adopted more widely.

Carbon benefits were also clear: geopolymer injection generated ~45% lower CO₂ emissions than cementitious alternatives, as verified by independent analysis.

The project was recognised across the sector, covered by the BBC, and commended by the Chartered Institution of Highways & Transportation.

 

Testimonial

Karl Brooks, Project Sponsor, Highways England:

“Geobear’s solution to the essential embankment repair at M11 Girton interchange has been a highlight of this year’s programme. The geopolymer injection provided an innovative response to voiding, allowing us to effectively manage this complex stretch of motorway. Monitoring of pavement heave was impressive, and the programme of delivery outperformed comparative methods. Collaboration with WSP and Interserve meant we met — and in some cases exceeded — the requirements of the network and our stakeholders.”

 

Ready to discuss your project?

Get in touch with our expert team today and discover how Geobear can extend the life of your critical infrastructure assets.

Bear pointing Bear pointing