Highways
Challenge
Severe voiding beneath the M11 northbound slip road threatened collapse at the Girton Interchange — traditional excavation repairs would have caused major disruption, delays, and safety risks.
Solution
Geobear stabilised the embankment with fast-curing geopolymer injection, restoring ground strength within tight tolerances, cutting disruption by five weeks, and reducing carbon emissions by 45%.
Carbon saving - 45% lower CO₂ emissions vs. cementitious grouting
High strength: ≥4 MPa compressive strength achieved with ±5 mm surface tolerance
Rapid delivery 3-week programme — 5 weeks faster than excavation
The northbound slip road at Junction 14 of the M11 — part of the Girton Interchange with the A14 and A428 — carries around 40,000 vehicles per day. As a critical link to Stansted Airport and strategic ferry ports, the route is a vital part of the UK’s Strategic Road Network.
Routine inspections by Highways England highlighted embankment issues at the M11 overbridge. Further ground investigation confirmed significant voiding beneath the carriageway close to the abutments. Left untreated, the defects risked severe settlement or even collapse, threatening safety and serviceability of the route at the same time as the adjacent A14 Cambridge–Huntingdon improvement scheme.
An urgent, non-intrusive solution was required to restore stability, avoid long closures, and maintain resilience on one of the busiest corridors in the East of England.
Client insight
Karl Brooks - Highways England
Geobear, working with Highways England, WSP, Interserve, and Kier Highways, designed and delivered an emergency geopolymer injection scheme:

The works were completed two days ahead of programme, within budget, and with no safety incidents. The carriageway was stabilised, risk of collapse eliminated, and the motorway reopened every morning, ensuring disruption was limited to overnight closures only.
Compared with excavation, the project avoided at least five weeks of disruption. This aligns with the Volterra Transport Study, which found that faster road maintenance on high-demand routes like the M11 can deliver £640–£7,400 of user savings per kilometre of works, with national annual savings of £70m–£87m if adopted more widely.
Carbon benefits were also clear: geopolymer injection generated ~45% lower CO₂ emissions than cementitious alternatives, as verified by independent analysis.
The project was recognised across the sector, covered by the BBC, and commended by the Chartered Institution of Highways & Transportation.
“Geobear’s solution to the essential embankment repair at M11 Girton interchange has been a highlight of this year’s programme. The geopolymer injection provided an innovative response to voiding, allowing us to effectively manage this complex stretch of motorway. Monitoring of pavement heave was impressive, and the programme of delivery outperformed comparative methods. Collaboration with WSP and Interserve meant we met — and in some cases exceeded — the requirements of the network and our stakeholders.”
Get in touch with our expert team today and discover how Geobear can extend the life of your critical infrastructure assets.