Subsidence repair without underpinning in Co. Clare

Challenge

Long-term subsidence caused extensive internal and external cracking on every elevation while foundation movement prevented the garage access door from operating, requiring a rapid, permanent stabilisation solution.

Solution

Geobear installed 52 geopolymer injection points beneath the foundations, strengthening weakened ground and monitoring drainage throughout the works to stabilise the property without excavation or underpinning.

4 days

Project completion

+50

Injection locations

10/10

Customer rating

Background

Geobear was appointed to stabilise a residential property in Co. Clare after long-term subsidence caused widespread structural movement.

Significant cracking had developed on every elevation of the property and was visible both internally and externally. Movement had also caused the garage access door to become inoperable, affecting the property's day-to-day usability.

The homeowner required a permanent, cost-effective solution that could be completed quickly while avoiding the disruption associated with traditional underpinning.

Challenge

Concrete underpinning was considered as a potential repair solution but was rejected due to the extensive excavation, prolonged programme and disruption involved.

Traditional underpinning would have required a minimum of six weeks on site, together with excavation, spoil removal and heavy construction equipment.

The challenge was to permanently stabilise the foundations while allowing the homeowner to avoid lengthy building works and major disruption.

Client quote

Does what it says on the tin. Dealing with Enda Gorman, the Irish point of contact for Geobear, was a pleasure from start to finish. Any issues were sorted straight away. Very professional company. Work completed within a week, with an engineer's report provided upon completion. Super job, would certainly recommend Geobear for any subsidence issues.

Attribution

Solution

Geobear designed a bespoke geopolymer injection solution to strengthen the ground beneath the affected foundations.

Over of 52 injection points were installed to depths of over 2m metres below foundation level. Through each injection location, carefully controlled quantities of expanding geopolymer were introduced into the weakened soils, where the material filled voids, compacted loose ground and restored foundation support.

Drain monitoring was carried out throughout the works to verify stability and ensure the effectiveness of the treatment.

The complete stabilisation programme was delivered in four days, with no excavation, spoil removal or heavy construction plant.

Results

The property was successfully stabilised with minimal disruption to the homeowner.

Compared with traditional underpinning, the Geobear solution delivered substantial programme and practical benefits:

  • Completed in four days instead of a minimum six-week programme.
  • +50 injection points installed.
  • Treatment depths over 2 metres.
  • Drain monitoring completed throughout the works.
  • No excavation or spoil removal.
  • No heavy construction equipment required.
  • Garage door functionality restored following stabilisation.
  • Customer awarded Geobear a 10/10 Net Promoter Score.