Challenge
A four-storey Islington property suffered severe subsidence, rotation and separation due to deep clay shrinkage. Traditional underpinning or rebuild options were slow, disruptive and financially prohibitive for the planned redevelopment.
Solution
Geobear stabilised the ground to 4.8 m and re-levelled the structure using phased geopolymer injection, restoring alignment with laser-controlled lifting — all completed in just nine days.
Project completed vs. 9–11 weeks for underpinning
Carbon emissions avoided (25.5% reduction)
Maximum controlled structural lift achieved

A property investor purchased a four-storey Victorian building, including a basement, in Hamilton Park, Islington, London, with plans to convert it into four apartments. However, the building exhibited long-term structural distress caused by clay shrinkage: significant subsidence, rotation, and separation from the neighbouring local-authority property were visible across the structure.
A site investigation identified severe desiccation in the clay extending to 4.8 m below basement level, alongside drainage defects contributing to ground softening. The building required stabilisation and controlled re-levelling before renovations could progress, but the tight site constraints and need to avoid major disruption demanded a solution far more efficient than traditional methods.
The investor explored two conventional options before selecting Geobear:
Traditional UnderpinningBoth options presented unacceptable disruption, cost, and time impacts. The client needed a faster, non-invasive approach that could:
Geobear implemented a two-phase geopolymer injection strategy designed to improve the ground and re-level the structural frame with minimal disruption.
A detailed site investigation was completed, including three boreholes to 5 m and a full drainage survey. This confirmed deep desiccation and weak soil conditions requiring improvement before lifting could begin.
Ground improvement works included:
This phase was completed in 5 days, enabling immediate progression to structural lifting.
Engineering data from detailed brick-course surveys enabled precise modelling of required lift.
The structural lifting phase was completed in 4 days, bringing the total programme to 9 days.


Geobear delivered a structural restoration programme that was significantly faster, cleaner, and more sustainable than traditional underpinning.
Customer testimonial
Wow it’s really fantastic! After experiencing structural issues at our Hamilton Park property, we were concerned about the safety, access and disruption traditional repairs would cause. Geobear’s treatment was remarkable — they stabilised our ground and achieved a 47 mm lift in just 9 days. Their non-invasive approach meant minimal disruption to our property. The speed and precision of the work was impressive and we’re delighted with the results. I wouldn’t hesitate to recommend Geobear to anyone facing similar foundation challenges. They delivered exactly what they promised with professionalism and expertise. Special thanks to Mr. Razwan for his outstanding support!