Utilities
Challenge
A failed sewer in Gorleston suffered 200 mm settlement and voiding due to ground washout. Excavation to 7.5 m depth was unfeasible in the busy town-centre junction.
Solution
Geobear injected geopolymer resin to 7.5 m depth, tripling soil strength, removing sinkhole risk, and enabling safe sewer relining — all completed ahead of schedule.
SPT values improved from 0–1 to 5–15
Targeted injections to 7.5 m beneath sewer alignment
Completed five days ahead of schedule
A road and sewer system managed by the Anglian Water One Alliance experienced severe settlement of 100–200 mm following flash flooding. The washout beneath a critical sewer pipe caused it to bow, with failed joints accelerating erosion and ground loss. This created the risk of a localised sinkhole and threatened service continuity.
Standard Penetration Testing (SPT) classified the ground beneath the sewer as very loose, with values between 0–1 at depths of 4.5–7.5 m. The client required the soils to be improved to at least medium density before relining works could proceed.
Traditional excavation to a depth of 6.5 m was ruled out. The site was in a constrained town-centre location — a busy road junction beside a supermarket. Full excavation would have required:
The client faced both engineering and logistical challenges.
From an engineering perspective, the soils were dangerously weak and required densification without excavation. Full pipe collapse was a risk if ground support was not reinstated. The treatment had to reach depths of 7.5 m in very loose, water-affected soils, while ensuring accuracy to avoid clashes with utilities.
From a logistical perspective, the works were located in a busy town centre. Excavation would have meant major disruption, extended road closures, and high community impact. Anglian Water needed a solution that was fast, precise, and minimally disruptive.
Client testimonial:
Anglian Water Alliance
Geobear worked closely with the Anglian Water Alliance to develop an innovative geopolymer injection programme.

The project was successfully completed ahead of programme and enabled full sewer relining to proceed safely.
Client Representative, Anglian Water Alliance:
“The unforeseen circumstances presented us with a particularly challenging situation. Geobear’s engineering team worked collaboratively with us to develop an innovative solution. The site team exceeded expectations and clearly met all of our objectives. The result was delivered ahead of programme, with ground conditions improved well beyond the requirement.
Get in touch with our expert team today and discover how Geobear can extend the life of your critical infrastructure assets.